FOUNDATION
SUPERSTRUCTURE
WALLS
ROOF
CEILING
FINISHES
WINDOWS
DOORS
IRONMONGERY
SANITARY FITTINGS
ELECTRICAL INSTALLATION
|
|
TV/FM POINTS
TELEPHONE POINTS
LIGHTING PROTECTION
PAINTING
WATERPROOFING
DRIVEWAYS & CARPARK
GATE AND FENCING
TURFING
RECREATIONAL FACILITIES
ADDITIONAL ITEMS
NOTES
|
|
FOUNDATION
Reinforced concrete driven piles.
Back To Top
SUPERSTRUCTURE
Reinforced concrete using Grade 35 concrete complying with SS26 and steel
reinforcement bar complying with SS2.
Back To Top
WAllS
External - common brick
Internal - common brick and/or block wall
Back To Top
ROOF
Pitched roof
- Clay roof tiles with aluminium foil insulation
- Tanalised timber roof rafters
Back To Top
|
CEILING
- Moisture resistant ceiling board to all bathrooms
- Fibrous plasterboard for kitchen
- Fibrous plasterboard for floors immediately below pitch roof only
- Skim coat with emulsion paint to other areas
Back To Top
FINISHES
A) Wall
- Internal
- Marble and wall plaster with emulsion paint for master bath
- Ceramic tiles and wall plaster with emulsion paint for bath 2. bath 3 and WC
- Ceramic tiles and wall plaster to kitchen (no tiles behind kitchen cabinet)
- Cement & sand plaster with emulsion paint to other areas
- Skim coat with emulsion paint finish to household shelter
- External
- Cement and sand plaster with exterior paint to exterior, balcony, private
enclosed space & roof garden.
- Common Areas
- Natural stone/ ceramic tiles finish and cement & sand plaster with emulsion
paint to lobbies at Ist storey
- Cement & sand plaster with emulsion paint to lobbies at basement, 2nd,
3rd and 4th storey
B) Floor
- Internal
- Marble with 100m high timber skirting to living and dining
- Marble to masterbath
- Ceramic tiles to bath 2, bath 3, kitchen, yard and WC
- Timber parquet with skirting to bedrooms and study
(no parquet under built-in wardrobes area)
- Cement sand screed finishes to household shelter
- External
- Ceramic tiles to private enclosed space, balcony and roof garden.
- Common Areas
- Natural stone/ ceramic tiles finish to lobbies at basement & lst storey
- Ceramic tiles to lobbies at 2nd, 3rd & 4th storey
- Natural stone/ ceramic tiles finish to swimming pool deck
- Natural stone pavior/ ceramic tiles/ premix to entrance driveway
- Granolithic finish to walkway & jogging tracks
Back To Top
|
WINDOWS
Powder coated aluminium framed windows with 6mm tinted float glass.
Back To Top
DOORS
- Solid timber door to main entrance
- Timber flush door to all internal doors
- Powder coated aluminium framed sliding doors with 8mm tinted float glass to living &
study at attic (where applicable)
- Powder coated aluminium framed swing doors with 8mm tinted float glass to study at
attic (where applicable)
- Timber swing door to yard toilet
- Metal blast door to Household Shelter
Back To Top
IRONMONGERY
Selected quality lockset to all doors
Back To Top
|
SANITARY FITTINGS
| Master bathroom |
1 long bath complete with bath mixer and shower set
1 vanity top with under counter basin and basin mixer
1 shower cubicle complete with shower mixer and shower set
1 pedestal water closet
1 soap/ sponge holder
1 soap holder
1 mirror
1 paper holder
1 towel rail
|
|
| Bath 2 & 3 |
1 vanity top with under counter basin and basin mixer
1 shower cubicle with shower mixer and shower set
1 pedestal water closet
1 soap holder
1 mirror
1 paper holder
1 towel rail
|
|
| W.C. |
1 wall hung basin with tap
1 shower tap and shower set
1 pedestal water closet
1 soap holder
1 paper holder
|
|
| Yard |
1 bib tap |
Back To Top
|
ELECTRICAL INSTALLATION
Concealed electrical wiring (except in yard and household shelters)
with adequate provision for lighting and power points.
Back To Top
TV/FM POINTS
Provision of TV / FM points suitable to receive Singapore Cable
Vision to living room, all bedrooms and attic study
(for attics without bedrooms). Refer to Electrical Schedule for details.
Back To Top
TELEPHONE POINTS
Provision of telephone points to living room, all bedrooms and attic study
(for attics without bedrooms). Refer to Electrical Schedule for details.
Back To Top
LIGHTNING PROTECTION
In accordance with Singapore Code of Practice CP33: 1996.
Back To Top
PAINTING
- Emulsion paint to internal wall
- Exterior paint to external wall
Back To Top
WATERPROOFING
Waterproofing to floor of kitchen, bathrooms, WC, yard, balcony and roof garden.
Back To Top
DRIVEWAYS & CARPARK
Concrete floor with hardener to basement driveway and carpark.
Back To Top
GATE AND FENCING
Brickwall/mild steel/chain link fencing
Back To Top
TURFING
Cow Grass
Back To Top
|
RECREATIONAL FACILITIES
- Swimming pool and wading pool
- Jacuzzi
- Children's playground
- Barbecue pits
- Exercise station and jogging track
- Clubhouse with multi-purpose hall and games room
- Changing rooms with steam room
- Gymnasium
- Tennis courts
- Musical garden
- Water feature
OTHER FACILITES
- Management Office
Back To Top
ADDITIONAL ITEMS
- Kitchen cabinets/ appliances: High and low laminated kitchen
cabinets with granite worktop, sink,
oven, hood and hob
- Air-conditioning"": Wall mounted split air-conditioning to
living and dining rooms, bedrooms and study
- Audio intercom provided to each unit
- Hot water supply to masterbath, bath 2 and bath 3
- Built-in wardrobe to all bedrooms except study
Back To Top
|
NOTES
* Marble are natural stone materials containing veins with tonality
differences. There will be colour and markings caused by their
complex mineral composition and incorporated impurities. While
such materials can be pre-selected before installation, this non-
conformity cannnot be totally avoided
** Air-conditioning system has to be maintained and cleaned on a
regular basis by the Purchaser. This includes the cleaning of filters
and clearing the condensate pipes to ensure good working
condition of the system
Back To Top
|
|
|
Developer: Northspring Development Pte Ltd
Legal Description: Lot 3459K MK 13 at Sembawang Road/Jalan Mata Ayer
Tenure of land: 99 Years leasehold w.e.f 25 February 1998
Developer's License No.: B 1378
Building Plan No.: BP A0819-121-1998-BP01 dated 2 August 1998 &
BP A0819-121-1998-BP02 dated 3 September 1999
Expected TOP: 30 November 2002
Date Of Legal Completion: 30 November 2005
Back To Top
|
The information contained herein are subject to changes as may be approved
by the relevant authorities and do not form part of an offer or contract.
All art renderings and pictures are aritsts' impressions or photo-library
photographs only and all areas stated herein are subject to re-survey.
While every reasonable care has been taken in providing the information
and specifications herein, the Owner and Developer cannot be held
responsible for any inaccuracy.
|