FOUNDATION
SUPERSTRUCTURE
WALLS
ROOF
CEILING
FINISHES
WINDOWS
DOORS
SANITARY FITTINGS
 

ELECTRICAL INSTALLATION
LIGHTING PROTECTION
PAINTING
WATERPROOFING
DRIVEWAYS & CARPARK
RECREATIONAL FACILITIES
ADDITIONAL ITEMS
NOTES




FOUNDATION
Cast in-situ concrete bored piles and micro piles.
Back To Top



SUPERSTRUCTURE
Reinforced concrete to beams, columns, slab and walls.
Back To Top



WAllS
All internal and external walls are constructed of common bricks.
Back To Top



ROOF
Reinforced concrete with appropriate waterproofing system on all flat roof.
Back To Top



CEILING
  • Fibrous plaster boards and painted with junction metal bead to living, dining, bedrooms, kitchen & bathrooms.
  • Storey shelter - skim coat and painted.
  • Reinforced concrete ledges, air-conditioning ledges and other mechanical and electrical ledges- skim coat and painted with appropriate waterproofing system, where necessary.

Back To Top



FINISHES
  • Wall
    1. Internal Wall
      Concrete or plaster with paint to living, dining and bedrooms. Stone finish to master bathroom (to false ceiling height and exposed areas only). Ceramic tiles to common bathrooms and toilets (to false ceiling height and exposed areas only).
    2. External Wall
      Concrete or plaster with paint.

  • Floor
    1. Internal Floor
      Stoneworks to living, dining, master bathroom, kitchen and storey shelter. Silestone to common bathroom. Homogeneous tiles to toilets. Timber flooring to all bedrooms.


    NOTE: Stoneworks are natural materials which by virtue of its complex mineral composition and natural impurities, contains veins and inherent variations in colour, tonality and density. Whilst the vendor may endeavour to install materials which are selected based on consistency, non-comformity cannot be avoided.

Back To Top



WINDOWS
Aluminium frames for curtainwall with double gazing.
Aluminium frames for windows with glass panel.
Back To Top



DOORS
Main entrance - half hour fire-rated timber door.
Bedrooms - timber brush door.
Master bathroom and kitchen - timber with glass insert door.
Back To Top



SANITARY FITTINGS
Master Bathroom 1 wash basin on granite counter top
1 shower stall with glass shower screen
1 water closet
1 toilet roll holder
1 towel rail
2 towel hooks
1 mirror

Common Bathroom 1 wash basin on granite counter top
1 shower stall with glass shower screen
1 water closet
1 toilet roll hoder
1 tower rail
2 towel hooks
1 mirror

Back To Top



ELECTRICAL INSTALLATION
Electrical wiring below false ceiling with the apartment shall generally be concealed, where possible.

Lighting, power, SCV and telephone points- adequate provision of the points.
Back To Top



LIGHTNING PROTECTION
Lightning protection system shall be provided in accordance with Singapore Standard CP33 : 1996
Back To Top



PAINTING
Internal - Emulsion paint.
External - Emulsion paint, spray textured coating.
Back To Top



WATERPROOFING
Waterproofing to bathroom, toilet, kitchen, yard, roof garden & changing room.
Back To Top



DRIVEWAYS & CARPARK
Floor hardener for driveway, ramp and car-park lot. Cobblestone to designated area of driveway.
Back To Top



RECREATIONAL FACILITIES
  1. Swimming Pool
  2. Gymnasium
  3. Barbecue pit
  4. Fitness station
  5. Waterscape
  6. Landscape
  7. Children playground
  8. Timber deck
  9. Changing Room

Back To Top



ADDITIONAL ITEMS
  1. Air-conditioning
          - ducted system to living and dining.
          - wall-mounted to bedrooms.
  2. Security system
          - CCTV.
          - audio video doorphone.
  3. Town gas supply for kitchen and water heater.
  4. Gas water heater for hot water supply to bathrooms and kitchen.
  5. Provision of SCV sockets only.
  6. Broadband and Internet only.
  7. Local Area Network (LAN) ready with Cat 5/5e cables to selected rooms within the unit.
  8. Proximity card key system for access side gate.
  9. Kitchen cabinets (with cooker hob and hood).
  10. Built-in wardrobes to all bedrooms.
  11. Remote control for autogate.

Back To Top



NOTES
* While every reasonable care has been taken while preparing this brochure, the developer and its agents cannot be held responsible for any inaccuracies. All statements are believed to be correct but are not to be regarded as statements or representations of fact. All information and specifications are current at tiem of print and subject to changes as may be required and cannot form part of an offer or contract. All plans are subject to any amendments approved by the relevant authority. Rendering and illustrations are artist's impression only and cannot be regarded as representations of fact. Floor areas are approximate measurement and subject to final survey.
Back To Top




Developer : TTH Developement Pte Ltd
Tenure of land : Freehold
Developer's Licence No. : B1449
Building Plan Approval No. : A1387-195-1999-BP01 (15 June 2000)
Planning Approval No. : P140599-14J5
Expected Date of Legal Completion : 31 December 2005
Expected Date of TOP : 31 December 2002

Back To Top